Start with the decision
Use a elevator modernization pre-bid visit to clarify conditions that the invitation cannot adequately describe. Prepare questions in advance, record what can and cannot be confirmed, and issue approved material clarifications to all bidders. A visit is not permission to investigate, disturb or alter the site.
This guide is for business-to-business project planning in the United States and Canada. For the wider trade context, visit the elevator modernization resource hub.
Questions to take to the visit
| Work area | Question | Record to reconcile |
|---|---|---|
| Controls and retained equipment | Who confirms that retained equipment is compatible with the proposed package? | existing car inventory, controller scope and components proposed for reuse |
| Doors and landing fixtures | Which floors and openings are in scope for each car? | opening and fixture schedules by car and served floor |
| Outage and return to service | Who confirms an elevator may return to service before the next outage begins? | car-by-car sequence, building access plan and acceptance milestones |
Download the elevator modernization site visit worksheet (CSV)
Fill in the response, owner or source, and date checked. Keep unresolved items visible. The file contains planning prompts only; it does not calculate quantities or make an approval decision.
Put the checklist to work
- Arrange authorized access with the project team and follow the site’s access instructions. Confirm which areas and documents may be photographed or shared.
- Discuss retained components, connections by other trades, temporary access arrangements and inspection coordination. Ask which assumptions can be confirmed during the visit and which require further information.
- Walk through the logistics affecting the equipment survey, building access, approved outage sequence and availability of the inspection parties. Note occupied areas, delivery routes and work windows without prescribing an installation method.
- Log each question with its location, respondent and required follow-up. Issue the approved response in the common clarification record.
A scope gap worth discussing
Illustrative example — not a Build Accord client project
One bid includes new landing fixtures on every served floor while another reuses selected fixtures. Ask for a floor-by-floor list and check that the proposals allow for the same staggered outages before comparing totals.
Apply this to your decision: A dated visit note and clarification log that improves the bid package without giving one bidder a private version of the scope.
Using this in the US and Canada
For a project in the United States
Record the state, local jurisdiction and actual service area. Confirm the project location and the scope of the business’s authority with the responsible project team. The U.S. Small Business Administration provides a starting point for business licensing resources.
For a project in Canada
Record the province or territory, municipality and actual service area. Use Canada’s permits and licences resources to locate relevant checks, including the linked BizPaL service. Confirm requirements for the actual activity and location.
For either market, state the currency, units and deadline time zone. This worksheet is general planning guidance, not a determination of licensing, procurement eligibility or technical compliance.
The next useful step
Continue with how to compare elevator modernization contractor quotes. For the other side of the conversation, see the elevator modernization bid proposal guide.