Start with the decision
Build the elevator modernization schedule around confirmed dependencies rather than a promised duration in isolation. The important inputs include the equipment survey, building access, approved outage sequence and availability of the inspection parties. Ask the contractor to state what must be ready before it can begin and what the following trade will receive.
This guide is for business-to-business project planning in the United States and Canada. For the wider trade context, visit the elevator modernization resource hub.
Plan the handoffs
| Package | Information needed before release | Completion handoff |
|---|---|---|
| Controls and retained equipment | existing car inventory, controller scope and components proposed for reuse | updated equipment inventory and the agreed controls documentation |
| Doors and landing fixtures | opening and fixture schedules by car and served floor | reconciled door and fixture schedule with the agreed functional records |
| Outage and return to service | car-by-car sequence, building access plan and acceptance milestones | inspection and acceptance records and a handoff to the operator and maintainer |
Download the elevator modernization schedule worksheet (CSV)
Fill in the response, owner or source, and date checked. Keep unresolved items visible. The file contains planning prompts only; it does not calculate quantities or make an approval decision.
Put the checklist to work
- Separate approvals, procurement, mobilization, installation and completion checks. Assign an owner to each release decision.
- Ask for the contractor’s stated availability and the date it was confirmed. Do not present an indicative window as a reserved crew.
- Resolve interfaces involving retained components, connections by other trades, temporary access arrangements and inspection coordination. Put decisions and deliveries that affect the sequence into the same schedule discussion.
- Agree how changes will be raised. Record the affected activity, revised assumption and who confirms the next workable date.
A scope gap worth discussing
Illustrative example — not a Build Accord client project
One bid includes new landing fixtures on every served floor while another reuses selected fixtures. Ask for a floor-by-floor list and check that the proposals allow for the same staggered outages before comparing totals.
Apply this to your decision: A dependency-based schedule discussion with named owners and confirmation dates, without invented standard durations or guaranteed delivery windows.
Using this in the US and Canada
For a project in the United States
Record the state, local jurisdiction and actual service area. Confirm the project location and the scope of the business’s authority with the responsible project team. The U.S. Small Business Administration provides a starting point for business licensing resources.
For a project in Canada
Record the province or territory, municipality and actual service area. Use Canada’s permits and licences resources to locate relevant checks, including the linked BizPaL service. Confirm requirements for the actual activity and location.
For either market, state the currency, units and deadline time zone. This worksheet is general planning guidance, not a determination of licensing, procurement eligibility or technical compliance.
The next useful step